Engineer’s Representative for NZS 3910 contracts

For councils, NZTA and asset owners running an NZS 3910 contract, directly or through the consultancy that holds it. Based in Mount Maunganui and on site when it matters.

Accreditation
NZTA Engineer to the Contract, Level 1
Contract forms
NZS 3910:2013 and 2023
Largest contract
$42.3M state highway bridge
Area
Bay of Plenty and Waikato

What you get

Someone running the contract on site under a written delegation from the Engineer, so the Engineer isn’t needed for every call that keeps the job moving.

  • Notices and instructions to the contractor that say what’s required and why, so it can be priced and programmed
  • Quantities and quality verified on site before anything is certified
  • Hold and witness points released on the record, not the programme
  • Variations and time claims assessed and put to the Engineer with the reasoning
  • Payment claims remeasured and verified item by item
  • Site meetings, minutes and a weekly report the client can actually use
  • Risk reviews plus health and safety and environmental inspections

Scale of the work

In 2024 I ran 2 Tauranga City Council contracts at the same time, the Oceanbeach intersection and the Welcome Bay roundabout. Between them that was 140 notices to the contractor, 47 variations, 13 payment schedules and 4 extensions of time, with both jobs in construction through the same months.

On the $42.3M SH29 Ōmanawa Bridge Replacement for NZTA the role covers weekly and monthly reporting to NZTA, progress meetings, fortnightly risk reviews and the assessment of payment claims, variations and extensions of time.

How I run it

Clear about the delegation

The delegation should be in writing and the contractor should have a copy, so everyone knows what the ER can decide. When something is the Engineer’s call, I prepare it and put it to them. I don’t guess past the line. More on what can and can’t be delegated →

Notices that can be priced

If a notice doesn’t say what’s required and why, the contractor can’t price or programme it and the argument just moves to later. When the Oceanbeach pavement came up 130 mm short of the existing levels with the kerbs pouring the next morning, the instruction set out the fix, classified it as a variation, said what records were needed to value it and opened the extension of time pathway, all in the same notice. What a notice has to carry →

Fair to both sides

Under NZS 3910 the role has to act fairly between the Principal and the contractor. In practice that means the reasoning has to hold up when the other side reads it. Sometimes it means telling the client something they’d rather not hear.

Records you can rely on later

Decisions get questioned months after they’re made. So the records are kept the same way on a small job as a large one. Every decision says what it was based on.

NZTA contracts

NZTA requires the Engineer to the Contract and the Engineer’s Representative on its construction contracts to be accredited at the right level for the contract value. I hold NZTA Engineer to the Contract accreditation at Level 1, current to August 2030. An application for full Engineer’s Representative Level 2 was submitted in September 2026.

I work in NZTA’s systems day to day: Active Risk Manager, Schedule 17 cost fluctuation, the monthly dashboard and Z05 health and safety plan review.

How it can work

  • Full time on site for the construction period
  • Part time across a contract, on site for the days that need it
  • Through the consultancy holding the contract, as a subconsultant. More for consultancies →
  • Direct to the council or asset owner

Projects: SH29 Ōmanawa · Oceanbeach · Welcome Bay · Sulphur Point · Mahuta Road · Other appointments