How NZ law and NZS 3910 fit together

Law sits at the top and a contract can’t override it. The contract sits under the law and the job runs inside the contract. Click any item to see what it is, which NZS 3910 clauses it touches and how it plays out on a job.

Written by
Tim Christie
Published
30 September 2026
Applies to
NZS 3910:2023 and 2013 and the NZ Acts around them
Format
Interactive map
Acts beat the contractWhere an Act applies despite the contract, like the Construction Contracts Act or the Health and Safety at Work Act, a clause that tries to avoid it has no effect.
The contract fills the spaceNZS 3910 is a published standard, not a law. It binds nobody until the parties sign it as their contract.
Specific beats generalSchedule 1 and special conditions change the General Conditions. NZS 3910:2023 adds an order of precedence in the Contract Agreement.
The job runs on processNotices, claims, schedules and Instructions on time and in the right form. That’s where most rights are won or lost.
A contract can’t override itA contract can vary or exclude parts of it

When it goes wrong: the dispute route under NZS 3910:2023

IC review6.4
Challenge a CA Instruction or IC Decision. Ends in a Final Decision.
Negotiate13.1
Notice of dispute, then the parties meet.
Mediation13.2
Confidential and not binding.
Arbitration13.3
Final and binding under the Arbitration Act 1996. Any dispute, not only Final Decisions.
Adjudication, any time13.4.3
A statutory right under the Construction Contracts Act. Runs alongside the contract steps. Keep working and keep paying (13.4).

Under NZS 3910:2013 the Engineer’s review and formal decision (13.2) was the gateway, with 1 Month time limits. Clause numbers on this page are NZS 3910:2023 with the 2013 equivalent shown. Act descriptions are short summaries for contract administration, not legal advice. Last checked 30 September 2026.

Common questions

NZ law and NZS 3910 questions

Can an NZS 3910 contract override the Construction Contracts Act?

No. The Construction Contracts Act applies despite anything in the contract. Pay when paid clauses have no effect and the right to adjudicate can’t be removed. NZS 3910 is written to work alongside the Act.

Is NZS 3910 a law?

No. It’s a standard form published by Standards New Zealand. It only binds the parties once they sign it as their contract, usually with Schedule 1 and special conditions that change parts of it.

Which Acts matter most on an NZS 3910 contract?

The Construction Contracts Act for payment, retentions and adjudication, the Health and Safety at Work Act for safety duties, the Building Act or the RMA for consents and the Heritage New Zealand Pouhere Taonga Act for archaeological finds.

What happens to the RMA references in NZS 3910:2023 now the RMA is being replaced?

NZS 3910:2023 uses the term Resource Management Law rather than naming the RMA, so references roll over to the replacement Acts. The RMA stays in force during the transition.

Can a safety obligation be passed to the contractor in the contract?

No. Under the Health and Safety at Work Act each business keeps its own duties and can’t transfer them by contract. Where duties overlap, the businesses must consult, cooperate and coordinate.